Project Duration
Stipulated Date of Commencement February 24 2014
Stipulated Date of Completion /
Likely Date of Completion
April 10 2014
Status
100%
Completed
Cost (₹)
Estimated at ₹ 2,221,634.00
Awarded for ₹ 2,113,317.73

Project highlights

Supply, Installation, Testing and Commissioning of CCTV, Biometric attendance and PA system

 
Gallery Image
Contractors
M/s. Reconnoitre Systems
Gallery Image
Consultants
M/s. KICONS Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Repairs/Upgradation & Maintenance of Government Schools in the State of Goa – Civil, Plumbing & Electrical works in Sanguem Taluka (Rate Contract)

View Project
Similar Project

Construction of new building and repairs of existing building for Government Higher Secondary School at Canacona – Erection of Distribution Transformer Centre (DTC) of 200 KVA

View Project
Similar Project

Repairs/Upgradation & Maintenance of Govt. Schools in the State of Goa- (Ponda Taluka) – (GPS Konse, GPS Makadsai, GPS Gothawada,GPS Kodar,GPS Bonbag & GPS Shignewhal )

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.