Status

Completed
 
Gallery Image
Contractors
Gallery Image
Consultants
 

Sub Works

This project involved 5 sub works. The details of the same available below

1

Interior work.

100% completed
 
Project Duration
Stipulated Date of Commencement February 15 2014
Stipulated Date of Completion /
Likely Date of Completion
May 15 2014
Status
100%
Completed
Cost (₹)
Estimated at ₹ 31,914,384.00
Awarded for ₹ 31,007,908.28

Project highlights

Providing interior furniture, false ceiling, parttions and other furnishings

 
Contractors
Contractors
M/s. T. S. Mistry,
Consultants
Consultants
M/s. KICONS Limited
2

Extension / upgradation of Government college of Arts, Science & Commerce at Khandola, Marcel, Goa – Fire Fighting work

100% completed
 
Project Duration
Stipulated Date of Commencement March 04 2014
Stipulated Date of Completion /
Likely Date of Completion
May 03 2014
Status
100%
Completed
Cost (₹)
Estimated at ₹ 2,664,951.00
Awarded for ₹ 3,327,405.00

Project highlights

Fire Fighting work

 
Contractors
Contractors
M/s. Suchi Turnkey Pvt. Ltd.
Consultants
Consultants
M/s. KICONS Pvt. Ltd.
3

Extension / upgradation of Government college of Arts, Science & Commerce at Khandola, Marcel, Goa – Supply, Installation, Testing and Commissioning of CCTV, Biometric attendance and PA system

100% completed
 
Project Duration
Stipulated Date of Commencement February 24 2014
Stipulated Date of Completion /
Likely Date of Completion
April 10 2014
Status
100%
Completed
Cost (₹)
Estimated at ₹ 2,221,634.00
Awarded for ₹ 2,113,317.73

Project highlights

Supply, Installation, Testing and Commissioning of CCTV, Biometric attendance and PA system

 
Contractors
Contractors
M/s. Reconnoitre Systems
Consultants
Consultants
M/s. KICONS Pvt. Ltd.
4

Extension / upgradation of Government college of Arts, Science & Commerce at Khandola, Marcel, Goa -HVAC work

100% completed
 
Project Duration
Stipulated Date of Commencement March 02 2014
Stipulated Date of Completion /
Likely Date of Completion
April 16 2014
Status
100%
Completed
Cost (₹)
Estimated at ₹ 2,863,663.00
Awarded for ₹ 2,749,999.50

Project highlights

HVAC work

 
Contractors
Contractors
M/s. Vighneshwar Air Conditioning Pvt. Ltd.
Consultants
Consultants
M/s. KICONS Pvt. Ltd.
5

Extension / Upgradation of Government College of Arts, Science and Commerce at Khandola, Marcel, Goa- Additional Miscellaneous Works

100% completed
 
Project Duration
Stipulated Date of Commencement November 10 2018
Stipulated Date of Completion /
Likely Date of Completion
March 09 2019
Status
100%
Completed
Cost (₹)
Estimated at ₹ 16,502,837.00
Awarded for ₹ 15,742,876.00

Project highlights

alteration to the interiors of the existing science block and other miscellaneous works

 
Contractors
Contractors
M/s. Deshpande Constructions
Consultants
Consultants
M/s. Kicons Limited
Similar Projects

See Similar Projects

Similar Project

Repairs/Upgradation & Maintenance of Government Schools in the State of Goa – Civil,Plumbing & Electrical works – Package B (Mormugao Taluka) GPMS Curpawada, GPMS Jetty.

View Project
Similar Project

Repairs of Govt. Schools in Pernem Taluka – Civil, Plumbing, Electrical works – Pernem Taluka: Package – I (GPS Pokewada Morjim, GPS Kattewada Morjim, GPS Vaidongar Parse, GPS BDL Parse, GPS Harmalkarwada Tuem, GPS Parsekarwada Harmal, GPS Madhalawada Keri)

View Project
Similar Project

Repairs and upgradation of Govt. High School in the State of Goa- Pernem Taluka- Package A

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.