Project Duration
Stipulated Date of Commencement
April 10 2015
Stipulated Date of Completion /
Likely Date of Completion July 09 2015
Likely Date of Completion July 09 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 21,184,374.00
Awarded for
₹ 16,708,003.14