Project Duration
Stipulated Date of Commencement
February 02 2019
Stipulated Date of Completion /
Likely Date of Completion January 05 2019
Likely Date of Completion January 05 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 20,390,309.00
Awarded for
₹ 18,968,719.00
Project highlights
Projects includes additional works of Air conditioning, Stage lighting, Stage diapery etc. in Mutipurpose hall
Contractors
M/s. Shrishti Enterprises
Consultants
M/s. Effective Architectural Services
See Similar Projects
Repairs/Upgradation & Maintenance of Government Schools in the State of Goa -Civil, Plumbing and Electrical works- Salcete Taluka- Package E (GPS Assolna, GPS Maina Curtorim, GPMS Bhati Curtorim, GPS Telaulim) (2nd call)
View Project
Reconstruction of Government Primary School at Vithalapur in Sankhali, Bicholim Taluka -Furniture works
View Project
Repairs/Upgradationl & Maintenance of Government schools in the State of Goa – Package C – Canacona Taluka (GPS Iddar, GPS Muthal, GPS Pantagal, GPS Talpan).
View Project