Project Duration
Stipulated Date of Commencement
May 08 2016
Stipulated Date of Completion /
Likely Date of Completion February 07 2017
Likely Date of Completion February 07 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 16,344,252.68
Awarded for
₹ 19,500,000.00
Project highlights
Repairs / Upgradation & Maintenance of Government High Schools at Netravali
Contractors
M/s. Shivam Infratech
Consultants
M/s. Nitin Arolkar