Project Duration
Stipulated Date of Commencement
March 08 2018
Stipulated Date of Completion /
Likely Date of Completion January 07 2019
Likely Date of Completion January 07 2019
Status
100%
Completed
Cost (₹)
Awarded for
₹ 8,163,033.37
Contractors
M/s. Bharti Infrastructure Developers
Consultants
M/s. Nitin Arolkar