Project Duration
Stipulated Date of Commencement
August 03 2018
Stipulated Date of Completion /
Likely Date of Completion July 01 2019
Likely Date of Completion July 01 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 7,833,369.37
Awarded for
₹ 8,163,033.37
Project highlights
Repairs/ Upgradation & Maintenance of schools
Contractors
M/s.Bharti Infrastructure Developers
Consultants
M/s.Nitin Arolkar
See Similar Projects
Repairs/ Upgradation & Maintaince of Government schools in the State of Goa – Civil, Plumbing & Electrical Woks – Canacona Package-II (GPS Baddem, GPS Avali, GPS Dabel, GHS Shristhal in Canacona Taluka)
View Project
Repair work at Government high school building at Gavalkhol, Canacona Goa on account of damages caused due to Cyclone Tauktae.
View Project
Interior works
View Project