Project Duration
Stipulated Date of Commencement
December 27 2021
Stipulated Date of Completion /
Likely Date of Completion April 26 2022
Likely Date of Completion April 26 2022
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,316,898.50
Awarded for
₹ 2,285,430.00
Project highlights
Erection of Distribution Transformer Centre (DTC) of 200 KVA for new and existing building of Government Higher Secondary School at Canacona.
Contractors
M/s.Siddharud Electricals
Consultants
M/s. Manoj M. Amshekar