Project Duration
Stipulated Date of Commencement
August 27 2018
Stipulated Date of Completion /
Likely Date of Completion September 10 2019
Likely Date of Completion September 10 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 17,411,783.00
Awarded for
₹ 18,467,663.19
Project highlights
Repairs/Renovation works
Contractors
M/s. Kamat Equipment Services
Consultants
M/S. Bhaskar wagle & associates