Project Duration
Stipulated Date of Commencement
June 14 2013
Stipulated Date of Completion /
Likely Date of Completion June 13 2014
Likely Date of Completion June 13 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 20,000,000.00
Awarded for
₹ 20,000,000.00
Project highlights
Repairs and renovation of roofing, to 25 number of Government Primary schools in Quepem & Canacona Talukas in this package.