Project Duration
Stipulated Date of Commencement
July 27 2013
Stipulated Date of Completion /
Likely Date of Completion July 26 2014
Likely Date of Completion July 26 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 20,000,000.00
Awarded for
₹ 20,000,000.00
Project highlights
Repairs/ Upgradation & Maintenance of schools
Contractors
M/s. M.B. Kinlekar
Consultants
M/s. Datta kare associates