Project Duration
Stipulated Date of Commencement
January 31 2019
Stipulated Date of Completion /
Likely Date of Completion October 09 2019
Likely Date of Completion October 09 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 12,953,520.88
Awarded for
₹ 14,737,217.90
Project highlights
Repairs/ Upgradation & Maintenance of schools
Contractors
M/s. Hari Krishna Constructions
Consultants
M/s. Datta kare associates
See Similar Projects
Construction of Higher Secondary School building for Dr.K.B.Hedgewar Higher Secondary School at Cujira, Bambolim,Tiswadi,Goa.
View Project
Interiors and Furniture work.
View Project
Renovation of GHS Ambaulim, Quepem
View Project