Project Duration
Stipulated Date of Commencement
August 07 2019
Stipulated Date of Completion /
Likely Date of Completion February 21 2020
Likely Date of Completion February 21 2020
Status
100%
Completed
Cost (₹)
Estimated at
₹ 6,179,573.00
Awarded for
₹ 7,179,784.80
Project highlights
Repairs/Upgradation & maintenance of Government Schools
Contractors
M/s. Savita Developers and Traders
Consultants
M/s. Vaishali Pednekar Associates