Project Duration
Stipulated Date of Commencement February 22 2014
Stipulated Date of Completion /
Likely Date of Completion
February 21 2015
Status
100%
Completed
Cost (₹)
Estimated at ₹ 21,708,909.00
Awarded for ₹ 24,912,755.00

Project highlights

Repair & reconstruction of the school building block

 
Gallery Image
Contractors
M/s. MM Naik
Gallery Image
Consultants
M/s. Prakash Lawande Associate
 
Similar Projects

See Similar Projects

Similar Project

Interior work.

View Project
Similar Project

Furniture work.

View Project
Similar Project

Construction of National Institute of Water Sports Campus at Caranzalem, Goa – Balance – Civil, Plumbing, Electrical, Fire Fighting and HVAC works

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.