Project Duration
Stipulated Date of Commencement
February 22 2019
Stipulated Date of Completion /
Likely Date of Completion July 22 2019
Likely Date of Completion July 22 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ Rate contract of Rs.50,00,000.00
Project highlights
Repairs/Upgradation and maintenance of Government schools in the state of Goa – Sattari Taluka and Pernem Taluka
Contractors
M/s. Sirajuddin Beig
Consultants
M/s. Manoj M. Amshekar
See Similar Projects
Repairs/upgradation & maintenance of Government primary Schools in the state of Goa -Civil, plumbing and electrical works-package A – GPS Ghadiwada GPS Deulmol Sirvoi, GPS Deulamol Markarnem and GPS Pontemol.
View Project
Repairs/Upgradation & Maintenance of Government Schools in the State of Goa – Civil,Plumbing & Electrical works-Package J – Sattari Taluka – GPS Kumbharkand, GPS Tamitgi, GPS Kesarkarwada, GPS Bagwada
View Project
Repairs/Upgradation and maintenance of Government schools in the state of Goa –Package B (Salcete Taluka) – (GPS Baradi, GPS Chandor, GMS Sao Jose de Areal, GPS Gudi Paroda) – 4th call
View Project