Project Duration
Stipulated Date of Commencement
Stipulated Date of Completion /
Likely Date of Completion July 15 2020
Likely Date of Completion July 15 2020
Status
100%
Completed
Cost (₹)
Estimated at
₹ 15,701,123.00
Awarded for
₹ 18,139,310.37
Project highlights
Repairs/Upgradation & Maintenance of Govt. schools in the state of Goa
Contractors
M/s. Sun Infrastructures
Consultants
M/s. Vaishali Pednekar Associates
See Similar Projects
Repairs/Upgradation and Maintenance of Government Schools in the State of Goa – Civil, Plumbing and Electrical works in :-Bardez Taluka – GPS Nagoa, GPS Verla, GPS Arpora, GPS Candolim.
View Project
Repairs/Upgratation & Maintenance of Govt Schools in the state of Goa – Package A (Sattari Taluka) – (GPS Gundelwada Velus, GPS Bhuipal, GPS Kopardem, GPS Dhamshe)
View Project
Reconstruction of GHS at Taramata bhile Surla in Bicholim Taluka
View Project





