Project Duration
Stipulated Date of Commencement
February 14 2019
Stipulated Date of Completion /
Likely Date of Completion August 28 2019
Likely Date of Completion August 28 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 5,765,344.00
Awarded for
₹ 6,453,546.81
Project highlights
Repairs/Upgradation and maintenance of Government schools in the state of Goa – Sattari Taluka
Contractors
M/s. MAI-TAT Associates
Consultants
M/s. Bhaskar Wagle and Associates