Project Duration
Stipulated Date of Commencement
April 24 2018
Stipulated Date of Completion /
Likely Date of Completion February 23 2019
Likely Date of Completion February 23 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 23,654,992.00
Awarded for
₹ 24,828,170.99
Project highlights
Repairs/Upgradation of School
Contractors
M/s. H. Candolkar & Sons
Consultants
M/s. Creative Abode.