Project Duration
Stipulated Date of Commencement
May 26 2019
Stipulated Date of Completion /
Likely Date of Completion December 11 2019
Likely Date of Completion December 11 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 10,264,411.00
Awarded for
₹ 11,676,091.37
Project highlights
repairs/upgradation
Contractors
M/s. Rakesh Kambli,
Consultants
M/s Mahimtura consultants(SLR Homes)
See Similar Projects
Infrastructure works for Sanjay Centre for Special Education at Bogda, Vasco – Electrical, Lift and Fire Fighting Works