Project Duration
Stipulated Date of Commencement
August 23 2018
Stipulated Date of Completion /
Likely Date of Completion September 06 2019
Likely Date of Completion September 06 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 12,338,948.00
Awarded for
₹ 12,891,812.60
Project highlights
Repair/Upgrdation works of schools which includes roofing ,tiling,dadoes,painting etc.
Contractors
M/s. Sandeep RS Khandeparkar
Consultants
M/s. Vaishali Pednekar Associates