Project Duration
Stipulated Date of Commencement
July 16 2015
Stipulated Date of Completion /
Likely Date of Completion November 15 2015
Likely Date of Completion November 15 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 5,607,355.05
Awarded for
₹ 6,429,577.99
Contractors
M/s. Kamat Engineering Services
Consultants
Creative Abode