Project Duration
Stipulated Date of Commencement
September 20 2017
Stipulated Date of Completion /
Likely Date of Completion September 19 2018
Likely Date of Completion September 19 2018
Status
100%
Completed
Cost (₹)
Estimated at
₹ 50,00,000.00
Awarded for
₹ 59,42,392.51
Project highlights
Repair/Upgrdation works of schools which includes roofing ,tiling,dadoes,painting etc.
Contractors
M/s. S M Realtors
Consultants
M/s. Vaishali Pednekar Associates
See Similar Projects
Repairs/Upgradation and Maintenance of Govt. schools in the state of Goa – Civil, Plumbing and Electrical works -Bicholim Taluka-Package G (G.P.S. Sal, G.P.S. Bhamai Pale, G.P.S. Lower Harvalem)
View Project
Construction of National Institute of Water Sports Campus at Caranzalem, Goa – Balance – Civil, Plumbing, Electrical, Fire Fighting and HVAC works
View Project
Repairs/Upgradation and maintenance of Government Schools in the state of Goa- Civil Plumbing and Electrical works:-Bicholim Taluka – Package K ( G.P.S Vathadev – Sarvan , G.P.S. Paltadwada, G.P.S. Naigini – Kudchire and G.P.S Kholpewadi – Sal )
View Project