Project Duration
Stipulated Date of Commencement
April 23 2014
Stipulated Date of Completion /
Likely Date of Completion June 06 2014
Likely Date of Completion June 06 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 4,999,658.00
Awarded for
₹ 4,999,658.00
Project highlights
Repair/Upgrdation works of schools which includes roofing ,tiling,dadoes,painting etc.
Contractors
M/s.S M Realtors
Consultants
M/s.Creative Abode