Project Duration
Stipulated Date of Commencement
September 29 2017
Stipulated Date of Completion /
Likely Date of Completion September 28 2018
Likely Date of Completion September 28 2018
Status
100%
Completed
Cost (₹)
Estimated at
₹ 5,000,000.00
Awarded for
₹ 5,000,000.00
Project highlights
Repairs of Govt. Schools in Pernem Taluka – Civil, Plumbing, Electrical works – Rate contracts
Contractors
M/s. H. Candolkar & Sons M/s. Sirajuddin Beig
Consultants
M/s. Vaishali Pednekar Associates