Project Duration
Stipulated Date of Commencement
March 16 2021
Stipulated Date of Completion /
Likely Date of Completion November 25 2021
Likely Date of Completion November 25 2021
Status
100%
Completed
Cost (₹)
Estimated at
₹ 14,933,469.00
Awarded for
₹ 15,109,063.37
Project highlights
Repairs/Upgradation and Maintenance of Govt. schools in the state of Goa
Contractors
M/s.Manup Infra
Consultants
M/s. Vaishali Pednekar Associates