Project Duration
Stipulated Date of Commencement
February 23 2019
Stipulated Date of Completion /
Likely Date of Completion September 22 2019
Likely Date of Completion September 22 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 10,935,425.00
Awarded for
₹ 12,205,472.53
Project highlights
Repairs/Upgradation of G.P.S Valshi, G.P.S. Ussap, G.P.S. Kharpal and G.P.S Dhangarwada
Contractors
M/s. Sirajuddin Beig
Consultants
M/s. Nitin Arolkar