Project Duration
Stipulated Date of Commencement
September 27 2018
Stipulated Date of Completion /
Likely Date of Completion October 12 2019
Likely Date of Completion October 12 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 19,791,190.00
Awarded for
₹ 22,795,741.42
Project highlights
Repairs/Upgradation and Maintenance of Govt. schools in the state of Goa
Contractors
M/s.Guru Constructions
Consultants
M/s. Bhaskar Wagle and Associates
See Similar Projects
Repairs/ Upgradation & Maintenance of Government schools in the State of Goa –Civil, Plumbing & Electrical works in Bardez Taluka :- GPS Betim, GPS Salvaor do Mund, GPS Paithona
View Project
Construction of Ashram school under Centrally sponsored scheme of Ministry of Tribal affaires at Moshiphond in the Village Ponguinim of Canacona Taluka.
View Project
Repairs/Upgradation and Maintenance of Govt. schools in the state of Goa – Civil, Plumbing and Electrical works-BicholimTaluka-Package E (G.P.M.S. Nanoda, G.P.M.S. Advalpal, G.P.S. Amthane)
View Project