Project Duration
Stipulated Date of Commencement
November 20 2018
Stipulated Date of Completion /
Likely Date of Completion July 04 2019
Likely Date of Completion July 04 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 5,401,746.32
Awarded for
₹ 6,015,143.88
Project highlights
Repairs/Upgradation and Maintenance work – Civil, Plumbing and Electrical works, sanitary work, land development, compound wall, etc.
Contractors
M/s. R.G. Contractors & Engineers
Consultants
M/s. Intrinsic Classics