Project Duration
Stipulated Date of Commencement
December 13 2018
Stipulated Date of Completion /
Likely Date of Completion December 27 2019
Likely Date of Completion December 27 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 10,601,898.00
Awarded for
₹ 12,390,267.82
Project highlights
School repair work (civil, plumbing & Electrical)
Contractors
M/s. Aditya P. Kamat Tarcar
Consultants
M/s Manoj Amshekar
See Similar Projects
Repairs/Upgratation & Maintenance of Govt Schools in the state of Goa – Package A (Sattari Taluka) – (GPS Gundelwada Velus, GPS Bhuipal, GPS Kopardem, GPS Dhamshe)