Project Duration
Stipulated Date of Commencement
July 17 2013
Stipulated Date of Completion /
Likely Date of Completion October 16 2013
Likely Date of Completion October 16 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 3,812,138.00
Awarded for
₹ 3,997,843.00
Contractors
M/s. Arken Solutions Pvt. Ltd.
Consultants
M/s. Gurudutt Sanzgiri