Project Duration
Stipulated Date of Commencement
January 15 2015
Stipulated Date of Completion /
Likely Date of Completion January 14 2016
Likely Date of Completion January 14 2016
Status
100%
Completed
Cost (₹)
Estimated at
₹ 16,825,899.00
Awarded for
₹ 20,759,886.19
Project highlights
Ground + 1 RCC storied building facilitating Panchayat Ghar , Multipurpose Hall, etc.
Contractors
M/s. Abhiyant Infratech Ltd.
Consultants
M/s. Keni & D’Souza
See Similar Projects
Fire Hydrant & Fire Alarm System.
View Project
Upgradation of Infrastructure in the rural areas under Deendayal Panchayat Raj Infrastructure Development (Golden Jubilee) Scheme , 2013 -Pernem Taluka : Construction of Panchayat Complex cum Multipurpose Hall at V. P. Querim – Tiracol