Project Duration
Stipulated Date of Commencement December 23 2013
Stipulated Date of Completion /
Likely Date of Completion
January 21 2014
Status
100%
Completed
Cost (₹)
Estimated at ₹ 43,897,049.00
Awarded for ₹ 41,694,835.00

Project highlights

• Consists of laying of 33 KV & 11 KV underground cables.
• Supply, installation, testing & commissioning of LED street light poles.

 
Gallery Image
Contractors
M/s. Goa Friends Engineering & Electricals Pvt. Ltd.
Gallery Image
Consultants
M/s. Kashec Engineers Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Development of road and allied works at Calangute.

View Project
Similar Project

Construction of Bridge at Dando Mollo in village panchayat Velsao-Pale in Cortalim constituency

View Project
Similar Project

Design and Construction of Bridge across River Mandovi at Panaji including approaches on NH 17 between Pundalik Nagar Junction (Porvorim) and Merces Junction

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.