Project Duration
Stipulated Date of Commencement September 21 2018
Stipulated Date of Completion /
Likely Date of Completion
December 21 2018
Status
100%
Completed
Cost (₹)
Estimated at ₹ 10,292,381.00
Awarded for ₹ 9,083,500.00

Project highlights

The scope of work includes:
1) Supply, installation, testing & commissioning of 33 KV, 3CX400 sq. mm, underground armoured cable – 4078 meters.
2) Supply, installation, testing & commissioning of 11 KV, 3CX300 sq. mm, underground armoured cable – 108 meters.
3) Dismantling of HT/LT overhead lines and Installation of new 100kVA distribution transformer centre.

 
Gallery Image
Contractors
M/s. Consistent Engineers
Gallery Image
Consultants
M/s. Nitin Arolkar
 
Similar Projects

See Similar Projects

Similar Project

Design and construction of bridge at Satrem – Construction of approach roads.

View Project
Similar Project

Construction Of new bypass road from Ambeudak Sanvordem to Devnamol in V.P. Kallem including drainage.

View Project
Similar Project

Construction of Bridge across Baga creek at Baga including approaches.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.