Project Duration
Stipulated Date of Commencement
March 31 2023
Stipulated Date of Completion /
Likely Date of Completion April 30 2023
Likely Date of Completion April 30 2023
Status
100%
Completed
Cost (₹)
Estimated at
₹ 12,495,124.80
Awarded for
₹ 9,944,036.82
Project highlights
The project consisted painting of Grade Seperator (02 Flyovers) on account of G20 Summit held in Goa in 2023.
Contractors
M/s. Perfect Engineers and contractors
Consultants
In-house (GSIDC)