Project Duration
Stipulated Date of Commencement
July 27 2014
Stipulated Date of Completion /
Likely Date of Completion December 31 2023
Likely Date of Completion December 31 2023
Status
100%
Completed
Cost (₹)
Estimated at
₹ 3,550,000,000.00
Awarded for
₹ 4,030,000,000.00
Project highlights
Bridge connecting Panaji and Porvorim of total lenght 5.44 km with cable stayed portion in the river spanning to 620m..
Contractors
M/s. Larsen & Toubro Limited
Consultants
M/s. TPF Engineering Pvt. Ltd.
See Similar Projects
Construction of Bus Stand at Honda.
View Project
Supply, Installation, Testing and Commissioning of flag mast system at the new bridge across river Mandovi at Panaji, Goa. SH: Supply of 20ftX30 ft National Flag
View Project
Design and Construction of bridge over river Kushawati at Adem, Sanguem Taluka.
View Project