Project Duration
Stipulated Date of Commencement
January 17 2018
Stipulated Date of Completion /
Likely Date of Completion January 21 2018
Likely Date of Completion January 21 2018
Status
100%
Completed
Cost (₹)
Estimated at
₹ 571,048.00
Awarded for
₹ 597,920.00
Project highlights
The scope of work includes dismantling of existing 33kV overhead lines and installation, testing & commissioning of 33 KV, 3C x 400 sq. mm, underground armored cable supplied by Goa Electricity Department.
Contractors
M/s. Pristine Engineering Services
Consultants
M/s. Rahul Deshpande