Project Duration
Stipulated Date of Commencement
November 05 2016
Stipulated Date of Completion /
Likely Date of Completion July 04 2017
Likely Date of Completion July 04 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 14,582,604.00
Awarded for
₹ 16,711,231.00
Project highlights
Repair upgradation of the pedestrain bridge with painting, tilling, utilies and other minor civil works
Contractors
M/s. Jagadish V. Pai
Consultants
M/s. LKS India Pvt. Ltd.