Project Duration
Stipulated Date of Commencement
February 26 2018
Stipulated Date of Completion /
Likely Date of Completion April 26 2018
Likely Date of Completion April 26 2018
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,399,120.00
Awarded for
₹ 2,820,440.00
Contractors
M/s. M. Venkata Rao Infra Projects Pvt. Ltd.
Consultants
M/s. Madhav Kamat & Associates