Project Duration
Stipulated Date of Commencement
January 19 2014
Stipulated Date of Completion /
Likely Date of Completion July 18 2015
Likely Date of Completion July 18 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 334,479,486.00
Awarded for
₹ 277,200,000.00
Project highlights
The project consists of two lane composite steel girder bridge of 220 m length along with approaches of 1600 m on Amona side and 500 m on Virdi side. The bridge lighting is of signature high quality LED fittings.
Contractors
M/s. M. Venkata Rao Infra Projects Pvt. Ltd.
Consultants
M/s. Madhav Kamat & Associates
Sub Works
This project involved 1 sub works. The details of the same available below
1
Design and construction of Bridge across River Zuari between Amona and Virdi. SH: Supply of LED Fittings, Poles and Brackets
100% completed
Project Duration
Stipulated Date of Commencement
February 26 2018
Stipulated Date of Completion /
Likely Date of Completion April 26 2018
Likely Date of Completion April 26 2018
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,399,120.00
Awarded for
₹ 2,820,440.00
Contractors
M/s. M. Venkata Rao Infra Projects Pvt. Ltd.
Consultants
M/s. Madhav Kamat & Associates
See Similar Projects
Construction of Bridge across Rua de Ourem Creek, Panaji – Shifting of 33 kV Overhead Lines
View Project
Improvement and Upgradation of the road from Borim Bridge Junction to Kamaxi Temple and Shivnath Temple in Shiroda Constituency.
View Project
Refurbishment of Pedestrian Bridge linking Central Library and creek.
View Project