Project Duration
Stipulated Date of Commencement
October 23 2012
Stipulated Date of Completion /
Likely Date of Completion November 02 2012
Likely Date of Completion November 02 2012
Status
100%
Completed
Cost (₹)
Estimated at
₹ 21,383,028.75
Awarded for
₹ 22,999,093.20
Project highlights
The RCC Simply supported Bridge is (Approx.) 35m in length comprising of 02 spans (approx. 17mts) supported by a central pier and on two abutment walls on both banks of the rivulet. •
The total length of approach roads is approx 400mts.
Contractors
M/s. Indiana Build Infrastructure Pvt. Ltd.
Consultants
M/s. Vijaykumar Sawant Associates (PMC)
See Similar Projects
Supply, Installation, Testing and Commissioning of flag mast system at the new bridge across river Mandovi at Panaji, Goa. SH: Supply of 20ftX30 ft National Flag
View Project
Construction of Minor Bridge across river Tar at Mapusa, Goa on MDR-14
View Project
Design and Construction of bridge over river Kushawati at Adem, Sanguem Taluka.
View Project