Project Duration
Stipulated Date of Commencement October 23 2012
Stipulated Date of Completion /
Likely Date of Completion
November 02 2012
Status
100%
Completed
Cost (₹)
Estimated at ₹ 21,383,028.75
Awarded for ₹ 22,999,093.20

Project highlights

The RCC Simply supported Bridge is (Approx.) 35m in length comprising of 02 spans (approx. 17mts) supported by a central pier and on two abutment walls on both banks of the rivulet. •
The total length of approach roads is approx 400mts.

 
Gallery Image
Contractors
M/s. Indiana Build Infrastructure Pvt. Ltd.
Gallery Image
Consultants
M/s. Vijaykumar Sawant Associates (PMC)
 
Similar Projects

See Similar Projects

Similar Project

Construction of Bus Stand & Market Complex at Pernem – Erecting 11 kV overhead line from feeder at the Electricity Department Substation to the Bus Stand Substation

View Project
Similar Project

Construction of Bridge for local farmers to cross river stream for cultivation of fields from Chune – Kator to Vanso Field in Village of Cumbarjua.

View Project
Similar Project

Widening and Improvement of MDR No.2 between chainage 3.40 Km to 9.12 Km from Merces to Goa Velha (Part).

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.