Project Duration
Stipulated Date of Commencement August 27 2006
Stipulated Date of Completion /
Likely Date of Completion
May 26 2007
Status
100%
Completed
Cost (₹)
Estimated at ₹ 66,755,638.12
Awarded for ₹ 75,996,000.00

Project highlights

Length of bridge = 42 m with footpaths on either side. The total length of approaches is 850 m with one additional pier in the middle.

 
Gallery Image
Contractors
M/s. M. Venkata Rao Infra Projects Pvt. Ltd.
Gallery Image
Consultants
M/s. Construma Consultancy Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Hotmiixing of road in Fatorda for Lusofonia Games

View Project
Similar Project

Design and Construction of Bridge across River Mandovi at Panaji including approaches on NH 17 between Pundalik Nagar Junction (Porvorim) and Merces Junction

View Project
Similar Project

Maintenance of bridges constructed by GSIDC for a period of five years (South Goa) :- Civil works.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.