Project Duration
Stipulated Date of Commencement March 18 2004
Stipulated Date of Completion /
Likely Date of Completion
November 17 2004
Status
100%
Completed
Cost (₹)
Estimated at ₹ 100,000,000.00
Awarded for ₹ 79,443,000.00

Project highlights

The Patto Bridge is 200 mts. in length, 12 mts. wide having geometrical features similar to the existing Patto Bridge. The foundations are pile foundations.

 
Gallery Image
Contractors
M/s. M. Venkata Rao Infra Projects Pvt. Ltd.
Gallery Image
Consultants
M/s. S.N.Bhobe & Associates Pvt. Ltd
 
Similar Projects

See Similar Projects

Similar Project

Improvement and Upgradation of the road from Borim Bridge Junction to Kamaxi Temple and Shivnath Temple in Shiroda Constituency.

View Project
Similar Project

Repairs and Resurfacing of PANAJI ROADS

View Project
Similar Project

Construction of Bus Stand & Mini Depot at Sankhali, Goa – Erection of 11KV line from Electricity Department feeder to bus stand substation.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.