Project Duration
Stipulated Date of Commencement
April 23 2011
Stipulated Date of Completion /
Likely Date of Completion July 22 2012
Likely Date of Completion July 22 2012
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,80,42,521.00
Awarded for
₹ 32,223,419.36
Contractors
M/s. SMC Infrastructures Pvt. Ltd.
Consultants
M/s. Design Ideas