Project Duration
Stipulated Date of Commencement
May 05 2004
Stipulated Date of Completion /
Likely Date of Completion May 25 2004
Likely Date of Completion May 25 2004
Status
100%
Completed
Cost (₹)
Awarded for
₹ 133,883.00
Contractors
M/s. Home Deco
Consultants
M/s. Rahul Deshpande & Associates