Status

Completed
 
Gallery Image
Contractors
Gallery Image
Consultants
 

Sub Works

This project involved 5 sub works. The details of the same available below

1

Civil & Electrical works

100% completed
 
Project Duration
Stipulated Date of Commencement November 25 2010
Stipulated Date of Completion /
Likely Date of Completion
February 25 2012
Status
100%
Completed
Cost (₹)
Estimated at ₹ 60,710,082.00
Awarded for ₹ 62,269,573.00

Project highlights

Construction of Bus stand having provison of 10 parking bay for buses, 4 commercial shops and other facilities. A mutipurpose hall with seating capacity of 800 with stage and changing rooms is attached to the Bus stand.

 
Contractors
Contractors
M/s. Shilpi Constructions
Consultants
Consultants
M/s. Rahul Deshpande & Associates
2

Phase I : Land Development.

100% completed
 
Project Duration
Stipulated Date of Commencement November 06 2008
Stipulated Date of Completion /
Likely Date of Completion
March 05 2009
Status
100%
Completed
Cost (₹)
Estimated at ₹ 7,891,687.00
Awarded for ₹ 7,300,000.00

Project highlights

Construction of Bus stand having provison of 10 parking bay for buses, 4 commercial shops and other facilities. A mutipurpose hall with seating capacity of 800 with stage and changing rooms is attached to the Bus stand.

 
Contractors
Contractors
M/s. Rohit Equipments
Consultants
Consultants
M/s. Rahul Deshpande & Associates
3

HVAC work.

100% completed
 
Project Duration
Stipulated Date of Commencement March 25 2012
Stipulated Date of Completion /
Likely Date of Completion
July 24 2012
Status
100%
Completed
Cost (₹)
Estimated at ₹ 3,420,639.00
Awarded for ₹ 3,539,999.00

Project highlights

Air conditioning works for Multipurpose hall

 
Contractors
Contractors
M/s. Aprant Motors Pvt. Ltd.
Consultants
Consultants
M/s. Rahul Deshpande & Associates
4

Acoustic work for Multipurpose Hall.

100% completed
 
Project Duration
Stipulated Date of Commencement May 06 2012
Stipulated Date of Completion /
Likely Date of Completion
November 05 2012
Status
100%
Completed
Cost (₹)
Estimated at ₹ 7,551,260.00
Awarded for ₹ 7,326,587.00

Project highlights

Acoustic works for Multipurpose hall

 
Contractors
Contractors
M/s. R. S. Lawande
Consultants
Consultants
M/s. Rahul Deshpande & Associates
5

External Electrical Work

100% completed
 
Project Duration
Stipulated Date of Commencement January 14 2013
Stipulated Date of Completion /
Likely Date of Completion
May 13 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 3,848,415.93
Awarded for ₹ 4,426,921.55

Project highlights

External Electrical Work

 
Contractors
Contractors
M/s. Ohm Engineers & Electricals Pvt. Ltd.
Consultants
Consultants
M/s. Rahul Deshpande & Associates
Similar Projects

See Similar Projects

Similar Project

Demolition Of Existing Bridge And Reconstruction Of Box Culvert On 18th June Road Over St. Inez Creek, Panaji

View Project
Similar Project

Design and Construction of Bridge across River Mandovi at Panaji including approaches on NH 17 between Pundalik Nagar Junction (Porvorim) and Merces Junction

View Project
Similar Project

Design & Construction of Bridge across river Zuari between Amona and Virdi.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.