Project Duration
Stipulated Date of Commencement
December 06 2016
Stipulated Date of Completion /
Likely Date of Completion December 05 2016
Likely Date of Completion December 05 2016
Status
100%
Completed
Cost (₹)
Estimated at
₹ 8,296,693.00
Awarded for
₹ 7,882,786.00