Status
100%
Completed
Project highlights
Construction of Bus stand having provison of 10 parking bay for buses, 4 commercial shops and other facilities. A mutipurpose hall with seating capacity of 800 with stage and changing rooms is attached to the Bus stand.
Sub Works
This project involved 5 sub works. The details of the same available below
1
Phase I : Land Development.
100% completed
Project Duration
Stipulated Date of Commencement
Stipulated Date of Completion /
Likely Date of Completion
Likely Date of Completion
Status
100%
Completed
Cost (₹)
Estimated at
₹ 7,891,687.00
Awarded for
₹ 7,300,000.00
Final Cost of Project
₹ 4,623,023.00
Contractors
M/s. Rohit Equipments
Consultants
M/s. Rahul Deshpande & Associates
2
Civil & Electrical works
100% completed
Project Duration
Stipulated Date of Commencement
Stipulated Date of Completion /
Likely Date of Completion
Likely Date of Completion
Status
100%
Completed
Cost (₹)
Estimated at
₹ 6,07,10,082.00
Awarded for
₹ 6,22,69,573.00
Final Cost of Project
₹ 86,264,969.00
Contractors
M/s. Shilpi Constructions
Consultants
M/s. Rahul Deshpande & Associates
3
HVAC work.
100% completed
Project Duration
Stipulated Date of Commencement
Stipulated Date of Completion /
Likely Date of Completion
Likely Date of Completion
Status
100%
Completed
Cost (₹)
Estimated at
₹ 3,420,639.00
Awarded for
₹ 3,539,999.00
Project highlights
Air conditioning works for Multipurpose hall
Contractors
M/s. Aprant Motors Pvt. Ltd.
Consultants
M/s. Rahul Deshpande & Associates
4
Acoustic work for Multipurpose Hall.
100% completed
Project Duration
Stipulated Date of Commencement
Stipulated Date of Completion /
Likely Date of Completion
Likely Date of Completion
Status
100%
Completed
Cost (₹)
Estimated at
₹ 7,551,260.00
Awarded for
₹ 7,326,587.00
Final Cost of Project
₹ 6,778,285.00
Project highlights
Acoustic works for Multipurpose hall
Contractors
M/s. R. S. Lawande
Consultants
M/s. Rahul Deshpande & Associates
5
External Electrical Work
100% completed
Project Duration
Stipulated Date of Commencement
Stipulated Date of Completion /
Likely Date of Completion
Likely Date of Completion
Status
100%
Completed
Cost (₹)
Estimated at
₹ 3,848,415.93
Awarded for
₹ 4,426,921.55
Project highlights
External Electrical Work
Contractors
M/s. Ohm Engineers & Electricals Pvt. Ltd.
Consultants
M/s. Rahul Deshpande & Associates
See Similar Projects
Construction of Bridge across Baga creek at Baga including approaches.
View ProjectLandscaping work.
View ProjectHot mixing & Improvement of Internal Roads in V. P. Navelim in Navelim Constituency.
View Project