Project Duration
Stipulated Date of Commencement
Stipulated Date of Completion /
Likely Date of Completion
Likely Date of Completion
Status
100%
Completed
Cost (₹)
Estimated at
₹ 58,697,913.00
Awarded for
₹ 86,684,891.00
Final Cost of Project
₹ 94,252,119.00
Contractors
M/s. M. Venkata Rao Infra Projects Pvt. Ltd.
Consultants
M/s. Madhav Kamat & Associates