Project Duration
Stipulated Date of Commencement
Stipulated Date of Completion /
Likely Date of Completion
Likely Date of Completion
Status
100%
Completed
Cost (₹)
Estimated at
₹ 613,673,260.91
Awarded for
₹ 548,475,269.00
Final Cost of Project
₹ 615,278,578.00
Project highlights
The bridge project is of significant importance to the villagers of Aldona and Calvim as the people were very much dependent on the ferry boat service plying between the two villages prior to the construction of the bridge. Construction of this bridge has mitigated the difficulties of the people in crossing the river, especially during the monsoon season. It is also proposed to promote Calvim village as a tourist spot. Thus, the bridge would help in providing easy access to the village
Contractors
M/s. M. Venkata Rao Infra Projects Pvt. Ltd.
Consultants
M/s. Madhav Kamat & Associates
See Similar Projects
Design and Construction of Bridge at Ambeshi – Ganjem over Mhadei river.
View ProjectConstruction of Road bridge at Balli in Quepem Constituency on Balli Fatorpa MDR road at Balli, Quepem.
View ProjectConstruction of Codal – Derodem bridge including approaches.
View Project