Project Duration
Stipulated Date of Commencement
December 24 2022
Stipulated Date of Completion /
Likely Date of Completion September 23 2024
Likely Date of Completion September 23 2024
Status
65%
Completed
Cost (₹)
Estimated at
₹ 56,011,510.00
Awarded for
₹ 56,965,003.68
Project highlights
Hostel Rooms with attached Toilets, Guest Room, Dining, Library, Indoor Games Room, Laundry, etc.
Contractors
M/s A.R. Construction
Consultants
M/s Amit Sukthankar